Construction Update
The steel for the Sanctuary roof is coming! Proctor Construction and their subcontractor were able to source the remaining specialty steel and delivery / erection is anticipated the last week of October. Expect to see a large crane onsite soon to raise all of the red metal supports followed by installation of the sanctuary roof!
To minimize delay to the schedule for Certificate of Occupancy, Proctor had other contractors working in the western side of the church. Normally, the following would have been sequenced after all the roofing was installed: Concrete decking, Interior stud wall framing, Electrical conduits and outlet placement, Canopy walkway overheads, and most notably the windows and doors on the west side. These activities were pulled up in the schedule to save time (and money).
To paraphrase a church member who saw the new windows, “Holy smokes Mike! Are all the windows that shade of blue?” Well, no. The bright blue tinting is just the interior and exterior protective film that will remain in place until the construction is finished. I promise you our church will not look like an aquarium when finished. 😊

Photo from the interior of the Breakout rooms

Photo of the exterior of the Narthex & canopy walkways

NOTE – The church committees elected to upgrade the originally specified green windows to a more appealing blue which also improves the solar reflectivity to lower cooling costs. A sneak peek of the actual color is shown below.