June 2026
Construction Update

We are going vertical!

The construction expression used when all foundations are poured followed by block and steel framing the building – an exciting time at this point in a project.

As shown in the diagram, our church structure is a complex bit of engineering to design and build. Although some of the concrete floors were recently placed, the main Sanctuary area will not be poured until most of the steel is in place. This is to allow cranes to operate within the Sanctuary while the church is built from west to east. One of the cranes will be a massive 140 ft tall. It will be a lot of crane work until we get all the roof decking installed, sometime in August. Then, the beautiful blue curtain wall windows will be installed.